Map
Reference
(see below) |
Location of Construction |
Construction Activity |
Road Closure |
Duration |
Information |
5 |
8th St West, 3rd Ave West and 3rd Avenue "A" West. 700 block vicinity (450m) |
Asphalt Paving to be completed in the spring of 2010. |
No
|
Spring 2010 |
See "What's New" on the home page for a complete list of construction Drawings |
7 |
9th St Bridge Over Sydenham River |
Replacement of the 9th St Bridge and Improvements to 9th St road and underground utilities from 1st Ave E to 2nd Ave W. Hydro One will be relocating poles starting mid June |
Currently 9th St Bridge is open to light vehicle traffic. Heavy trucks are prohibitied from using t
|
Construction is expected to start mid to late June 2010 |
During construction in 2010 the bridge will be closed to traffic and a detour will be provided. Additional formation will be provided later in 2010 |
8 |
9th St E and 9th St W from 3rd Ave W to 1st Ave E, 2nd Ave W from 100m North and South of the intersection |
Bell telephone communication cables installation |
NO
NO |
Construction COMPLETED April 2010 |
This Project is COMPLETE |
|
10th Street East from Lamson Crescent to 16th Avenue East. |
New road construction.
Phase 1 includes underground utilities, retaining wall and road base construction. |
Construction activities are limited to the unopened road allowance. No through traffic is allowed.
|
Phase 1 Construction to be completed spring 2010 |
Information on this project can be obtained by contacting Engineering at 519 376 4530.or Gamsby and Mannerow at 519 376 1805 |